Do you have the confidence to pass the IT exam without CCM study materials? Do you know how to prepare for the IT exam? And have you found any useful study materials for the IT exam? If your answer is "No" for these questions, congratulations, you have clicked into the right place, because our company is the trusted hosting organization refers to the CCM practice questions for the IT exam. With the help of our CCM study guide, you can pretty much rest assured that you can pass the IT exam as well as obtaining the IT certification as easy as blowing off the dust, because our Medical Professional CCM training materials are compiled by a large number of top IT exports who are coming from many different countries. CCM study materials in our website are the most useful study materials for the IT exam, which really deserves your attention.
One year free renewal
For the sake of the interests of our customers, we will update our CCM practice questions regularly to cater to the demand of them. Our experts will spare no effort to collect the latest information about the IT exam, and then they will compile these useful resources into our Medical Professional CCM study materials immediately. Therefore, we won't miss any key points for the IT exam. What's more, we will provide the most useful exam tips for you. There is no doubt that with the help of our CCM study guide, it will be a piece of cake for you to pass the IT exam and get the IT certification. Customer satisfaction is our greatest pursuit. We will continue to update our CCM actual real questions, and to provide customers a full range of fast, meticulous, precise, and thoughtful services.
Enjoy the fast delivery
There is no denying that everyone wants to receive his or her CCM practice questions as soon as possible after payment, and especially for those who are preparing for the exam, just like the old saying goes "Time is life and when the idle man kills time, he kills himself." Our CCM study materials are electronic products, and we can complete the transaction in the internet, so our operation system only need a few minutes to record the information of you after payment before automatically sending the CCM study guide to you by e-mail. You can download and use our training materials only after 5 to 10 minutes, which marks the fastest delivery speed in the field.
Sound system for privacy protection
It is universally acknowledged that our privacy should not be violated while buying CCM practice questions. Our company makes much account of the protection for the privacy of our customers, since we will complete the transaction in the Internet. Our company has made out a sound system for privacy protection. First of all, our operation system will record your information automatically after purchasing CCM study materials, then the account details will be encrypted immediately in order to protect privacy of our customers by our operation system, we can ensure you that your information will never be leaked out. In order to make customers feel worry-free shopping about Medical Professional CCM study guide, our company has carried out cooperation with a sound payment platform to ensure that the customers’ accounts, pass words or e-mail address won't be leaked out to others.
Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions:
1. (Under the FIDIC Red, Yellow, and Silver Books (1999 editions), the Engineer/Employer shall be entitled to withhold from the release of retention money the estimated cost of any work which remains to be executed under Clause 11 (Defects Liability) in the Red Book or under Clause 12 (Tests after Completion) in the Yellow and Silver Books. Is this statement true or false?)
A) True
B) False
2. You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999). You work for the Employer - a highway management agency. During the tender period, you are informed of a specific Commencement Date required by the directors of the agency. Which two of the following approaches to inform the tenderers of this date are clearly and unambiguously drafted?
Choose all of the correct answers (multiple possibilities).
A) Inform the Commencement Date to the tenderers by email, and attach that email in the list of Contract Documents.
B) Specify Commencement Date in the Minutes of Meeting of Contract Negotiation.
C) Specify Commencement Date in the Contract Agreement.
D) Specify Commencement Date in the Particular Conditions.
3. The Employer has prepared a contract for a waste-to-energy project based on the FIDIC Yellow Book (edition
1999). You are preparing negotiations on behalf of one of the Subcontractors with the Contractor. The main Contractor will manage the design and build of the Works, whereby the Subcontractor will deliver critical systems regarding power generation and cooling. The Contractor intends to contract the main Contract back- to-back with the Subcontractor. In the proposed back-to-back subcontract, the following amendment is proposed through Particular Conditions:
" Sub-Clause 4.4. The following paragraph is added: The Subcontractor is required to scrutinize the Employer
' s Requirements in a manner identical to the obligations of the Contractor as stated in Sub-Clause 5.1 of the Main Contract. The Subcontractor will indemnify and hold harmless (up to the maximum liability of the Subcontractor) the Contractor with regard to any error, fault or other defect found in the Employer ' s Requirements, its items of reference or Contractor ' s design of the Works for the scope part for which Subcontractor is contracted. " What is your advice to the Subcontractor (SC) in regard to entering this proposed subcontract?
A) I would advise the SC not to enter this contract, because Sub-Clause 4.4 describes the obligations of SC towards Contractor, but this amendment positions the SC in a vulnerable position for claims regarding all errors, faults or other Defects (whether originating from the Employer ' s Requirements or the design of the Contractor). Essentially, this means the SC becomes liable for the design part, which is within the scope of Contractor even without SC having the opportunity to review it.
B) I would advise the SC not to enter this contract because the Contractor is obliged to act in accordance with good faith. A proposed paragraph like this opposes good faith.
C) I would advise the SC to enter the Contract with the request to the Contractor to delete this amendment in the Particular Conditions. If the Contractor does not agree to do so, at least the Subcontractor has tried its best.
D) I would advise the SC to discuss this amendment with the insurance company just to be sure there will be no transfer of risks. This amendment is mainly a consequence of the FIDIC Yellow Book structure, where the Contractor has obligations in terms of scrutinizing the Employer ' s Requirements. This amendment makes this obligation more explicit. If the insurance company has no problems with insuring the parts which will be delivered by SC to Contractor, the SC can accept this risk and enter into the subcontract.
4. You are the Contract Manager for the Engineer in a hospital project using FIDIC Yellow Book (edition 2017).
The Employer demands perfection in the project ' s design and construction quality. There are many Variations initiated by the Employer during design and construction. Which one of the following is considered to be a valid Variation?
A) The Contractor submits a Value Engineering proposal regarding the lighting system for the operation rooms. The Engineer is positive about the proposal and tells the Contractor they need to look into it.
B) The Engineer instructs a change in slopes of the access road to the intensive care unit to meet the Employer ' s Requirement. The Engineer does so with a Notice in accordance with Sub-Clause 3.5.
C) The Engineer requests a proposal regarding a change in type of windows and doors. The Contractor submitted the proposal accordingly to the Engineer. The Engineer instructs the Variation.
D) The Employer verbally instructs a change in the type of doors. The Engineer issued a Notice describing the required change and denying any costs for the Contractor.
5. If defects are identified during the Tests on Completion, which one of the following options is not available to the Parties under the Contract?
A) The Party which is not liable for the cost of rectifying defects can expect the other Party to pay the cost of performing the repeated tests.
B) If the defects do not affect the use of the Works for their intended purpose, the Engineer can issue the Taking-Over Certificate.
C) By giving reasons, the Engineer can refuse to accept the Works until repeated tests have been successfully performed.
D) The Employer can request to take over the Works.
Solutions:
| Question # 1 Answer: A | Question # 2 Answer: C,D | Question # 3 Answer: A | Question # 4 Answer: B | Question # 5 Answer: A |